Completed projectsTOYODA GIKEN VIETNAM – The SECONDARY FACTORY PHASE 1 PROJECT

TOYODA GIKEN VIETNAM – The SECONDARY FACTORY PHASE 1 PROJECT

Project Introduce

Civil Work: 01 storey Factory, Steel structure, EPS panel + Iron wall cover & roofing work. Brick wall to elevation 1.15m to top is metal wall. Floor by Floor Hardener. Office & Canteen area, ceramic tile for floor, gypsum ceiling board

M&E Work: HF lighting system, Fire & fighting system, A/C system, Cooling Pad Fan System, Air compressor system, Waste water treatment, water suply system, …

Investor TOYODA GIKEN Vietnam Co., Ltd.
Project scale 3,256 m2
Commencement date 25/08/2015
Finishing day 15/01/2016