Civil Work: Metal sheet with insulation form elevation fl+0.3 up to the roof level. Deck plate for 2st floor. Metal roof sheet with insulation for boundary wall. Utility with loading yard & dock leveler system. Utility system is included
M&E Work: Semi cleaning room at tooling area, production area with AHU system. Compressor, clean water…. system including.
Investor | Santomas Vietnam JSC. |
---|---|
Project scale | 6,200 M2 |
Commencement date | 30/11/2016 |
Finishing day | 04/06/2017 |
Civil Work: Metal sheet with insulation form elevation fl+0.3 up to the roof level. Deck plate for 2st floor. Metal roof sheet with insulation for boundary wall. Utility with loading yard & dock leveler system. Utility system is included
M&E Work: Semi cleaning room at tooling area, production area with AHU system. Compressor, clean water…. system including.