Civil Work: 01 storey Factory, Steel structure, EPS panel + Iron wall cover & roofing work. Brick wall to elevation 2.30m to top is metal wall. Floor by Epoxy paint 1mm thickness, Floor Hardener. Office & Canteen area, ceramic tile for floor, gypsum ceiling board

M&E Work: HF lighting system, Fire & fighting system – Sprinkler system, A/C system, Cooling Water System, Air compressor system, Generator system, Waste water treatment, water suply system, …

Investor 大塚産業マテリアルベトナム株式会社
Project scale 6,120m2
Commencement date 01/10/2016
Finishing day 15/05/2017
大塚産業マテリアルベトナム工場 フェース1プロジェクト

Project Location

Civil Work: 01 storey Factory, Steel structure, EPS panel + Iron wall cover & roofing work. Brick wall to elevation 2.30m to top is metal wall. Floor by Epoxy paint 1mm thickness, Floor Hardener. Office & Canteen area, ceramic tile for floor, gypsum ceiling board

M&E Work: HF lighting system, Fire & fighting system – Sprinkler system, A/C system, Cooling Water System, Air compressor system, Generator system, Waste water treatment, water suply system, …

Project Images

otsuka-sangyo
ohtsuka-2
C4 (1)
C2

Contact

    Images
    Messenger Zalo Tel Back to top